Final Report
On the
Relocation of the
Arlington Duplicate Bridge Club
Overview
The Board of Directors requested a
review of the relocation of the Club in order to evaluate the reasonableness of
the final costs associated with preparing the new facility. This report contains a review of the
chronology of the relocation, with specific emphasis on the events that
influenced the decisions relating to cost, a summary of the key items wherein
the original estimate and the final cost differed significantly, and a summary
of other topics associated with the costs, principally a summary of unusual actions
implemented through the Relocation Committee in order to reduce the costs to
the benefit of the Club.
The sources of the data for this
assessment were the following:
It should be noted that all bills
due to the prime contractor and his subcontractors have been paid. In addition, the reimbursement check of
$20,040 from Cencor (negotiated as a renovation allowance in our basic lease)
has been received. The interim financing
during the renovation period was graciously provided without interest by three
members of the Club; they have been reimbursed. Thus, all costs associated with the renovation and move have been
settled in full.
Chronology of the Relocation
In summer of 2005, there was an
armed robbery at the previous facility at 2136 North Collins. Fortunately there were no injuries during
the event. However, that punctuated the
continuing concerns regarding the long-term future of the club in that location. Several members suggested that the Club
seriously consider a move to a more favorable location. Lauren Brown and Dee Berg initiated a search
for potential locations, and were referred to Bryan Graham, a commercial
realtor who eventually became our representative in the relocation. Bryan generated a list of sixty-three
potential sites in Zip Codes 76011 and 76012.
Lauren and Dee did considerable
research and evaluation and condensed the initial list to six sites for further
investigation. Although the Board had
executed an extension to the lease of the facility on North Collins, they
agreed to endorse a committee to develop alternatives for relocation. Lauren Brown was appointed Chairperson of
the Relocation Committee.
The Relocation Committee quickly focused in on two
potential sites in Fielder North Plaza, both of which required significant
renovation in order to be suitable for the Club’s purposes. Jim Brown requested Steve Loe, a general
contractor with over ten years record of performance for construction and
remodeling for Don Davis Auto Group (Jim’s employer), to look at the sites and
give an informal assessment of minimum renovation costs. Steve met with the Committee at the larger
Fielder Plaza location on the next visit and provided an “off the cuff”
estimate of $30,000 to $35,000 to provide the minimal work necessary to move
in. Once we received rental costs on
that space, it was determined that it would be completely out of reach of our
budget. We then decided to look again
at the smaller space at Fielder Plaza.
Once again Steve looked at the property with the Committee. Steve indicated that he thought if we cut
corners, that we might be able to get it done for $25,000 to $35,000, depending
upon the addition of expanded restroom facilities. Jim Brown then asked if he (Steve) knew of anyone who might work
on such a small project. Much to Jim’s
surprise, Steve said that he would take on this project, with Jim as the
liaison between him and the Committee.
As the Relocation Committee moved
forward, it became apparent that the smaller Fielder Plaza property (the one we
now occupy) would be the selected candidate.
At Jim’s request, Steve conducted a walk-through of the facility (a
difficult task, as there was at that time no electricity in the unit) and gave
an initial estimate of $34,638 (including the expanded women’s restroom), so we
could develop our presentation to the membership. At that point, we thought, based on Bryan’s best guess, that we
might be able to get $25,000 to $30,000 finish-out allowance. Jim asked Steve if he thought there might be
any chance of completing the project for $25,000; he said that it might be
possible, but would depend on many factors.
He was not familiar with the property and did not have any idea what we
might find in the walls and ceilings.
He said he should be able complete the renovation in about two to three
weeks. If we could cut as many corners
as possible and find members willing to donate some work and supplies, we might
be able to accomplish the feat. He said
that if it would help us get the club, he would be willing to waive his fee (a
little over $4,000).
The committee developed a
presentation for the membership, detailing the incidents leading up to the
search for a new location, the selected property, the monthly costs and the
estimated finish-out costs and allowance.
There was a Special General Membership Meeting on 12 November 2005. When the relocation proposal was presented
to the membership, it was overwhelmingly approved.
The Committee continued to work with
Bryan and Kathryn McGlinchey (an attorney at Cary Jennings’ law firm, who
donated these services at no cost to the club) to negotiate the lease contract
language, monthly rent and finish-out allowance with Cencor. After much hard work, we negotiated a
finish-out allowance of $20,040 plus the first two months rent free (a total of
$5,010) for a total of approximately $25,000.
We next found out that our current
sign did not meet the shopping center’s specifications and would have to be
replaced with a new sign. Bryan
referred Jim to Van Waugh with Sign-A-Rama, who had made our sign for the Collins
street location. Van provided an
estimate of approximately $3,000 for the signs. Jim was able to get Van to give us a 20% reduction, since he had
recently made our other sign. Bryan generously
agreed to forego $2,500 of his commission to cover the cost of the sign.
The Committee learned that an
independent asbestos survey would be required, resulting in an impact to both
cost and schedule. There was a
significant delay in securing electricity for the new facility, due to the fact
that the unit had apparently been subdivided and the meters were not properly
marked and certified. Cencor provided
an electrician to trace and certify the wiring, and after a delay, Jim Brown
was able to meet TXU late one evening to get the electricity turned on so that
construction could begin.
A similar delay occurred in getting
gas hook-up, and once again Cencor provided a plumber at their expense to
repipe for the gas hook-up. Jim Brown
handled final arrangements with the gas company in order to allow for obtaining
the Certificate of Occupancy.
Final Cost of Renovation
The final invoiced cost, paid to
Steve Loe and used to obtain our $20,040 renovation reimbursement from Cencor,
was $33,353.55. The original estimate (10
November 2005) was $34,638. This was
the baseline from which the Relocation Committee started, with the objective
being to “cut corners” as much as possible, hoping to come in with a final cost
of near $25,000 (which would have resulted in zero out-of-pocket to the Club,
based on Cencor’s providing $20K cash and two months rent-free at $2500
each). An assessment of the actual
final costs reveals that most of the items in the original estimate came in reasonably
close to the estimate. There were, in
fact, only five items that drove the $8300 overrun. There are reasonable explanations for each of these variances,
and they are summarized in the table below.
|
Item |
Original Estimate |
Actual Invoice Cost |
Difference |
Explanation |
|
Plumbing |
$2400 |
$5500 |
$3100
(+130%) |
Problems
with the existing plumbing (location and condition of the lines). A much larger amount of concrete had to be
removed to get to worn out plumbing lines that had to be replaced, in addition
to running the needed new lines for the expanded restrooms. The layout of the plumbing was not as expected,
as the two restrooms had apparently been added at different times and the
plumbing was not aligned with the needed location of the walls. |
|
Electrical |
$1600 |
$4259.35 |
$2659.35
(+166%) |
Although
we did not have to purchase any additional fluorescent fixtures, almost all
of the fixtures were rearranged and aligned, rather than just spreading the
existing fixtures around to obtain adequate light. Spot lights were added along the pathway on the north wall of
the middle playing room. Ceiling fan
supports and wiring were added to both rooms. Additional electrical outlets were added to accommodate the
director’s desks and other needs.
Light switches were added in every room (in place of turning on the
lights at the breaker panels), and switches were added for the fans in both
rooms (rather than using the pull cords on the fans). A new circuit had to be added to
accommodate the exterior sign. An
emergency exit sign had to be added by the storage closet, since the emergency
exit over the back door could not be viewed around the closet. |
|
Carpet |
$4050 |
$5506.43 |
$1456.43
(+36%) |
Original estimate was for 2,500 square feet of carpet. Ended up carpeting the entire facility (except the restrooms) for around 3,200 square feet of carpet. We also did not receive any of the donated carpet squares as had originally been anticipated. |
|
Panic Bar for Rear Door |
$0 |
$480 |
$480 |
Unable
to move the one from the Collins facility as had been planned. |
|
Ceiling Grid in East Playing Room |
$2416 |
$3326 |
$910
(+38%) |
Apparently
this was simply a case of material costs exceeding the estimate. |
It should also be recognized that
the Relocation Committee took many extraordinary steps to contain costs. There were also donations of time and
services from the membership of the Club.
A summary of the key elements is the following:
Thus, it should be recognized that
these contributions resulted in cost avoidances to the Club of about $9000
(exclusive of the HVAC, which alone is nearly $20,000).
Summary
Although there was initial concern
about the $8300 out-of-pocket cost to the membership, analysis has yielded the
following conclusions:
An overwhelming majority of our club
members and guests have remarked on the high quality of our new facility. The facility meets the objectives originally
identified by the Relocation Committee in the presentation to the Special
Membership Meeting in November. It
provides a much larger playing facility in an area not identified as a high
risk for crime. We have ample well-lit
parking and visible onsite security patrols.
The increase in the monthly rent will initially be funded through the
modest $1 increase in card fees authorized by the membership. Lighting and ambient noise allow for a much
more comfortable playing environment.
Finally, access via the freeway system has been upgraded over the
Collins Street facility.
Recommendation
With the completion of this review, it
is recommended that the Board of Directors take the following actions:
In addition, it is recommended that
the Board provide special recognition to the key members of the Relocation
Committee for their countless hours of over-and-above tasks that were critical
in identifying the site and managing the renovation – Jim Brown, Lauren Brown,
Dee Berg, and Jack Muzzio.
Submitted
to the Board of Directors on 12 April 2006.
______________
C.C.
Burke
Reviewed
by the ADBC Board of Directors on 2 May 2006; approved as submitted herein.
_______________
Caron
Peck 5/3/06